Your project team is on its way to finish work on the project, while you have the impression that a staff member is already negotiating the next assignment in another project. You are afraid that the person may come under pressure to start working on the other job before she has finished her work for your project. Her task is very complex, and it would be hard for someone else to take up the partial results and finish them. What action is most likely to resolve the situation?

1
sentiment_very_satisfied
by
מיין לפי

You are running a project which was budgeted based on some rough order of magnitude (ROM) estimates with a precision of -50% /+100%. Meanwhile, with new estimates made on detail level and some work already finished, you found out that these estimates were consistently too low and the budget will not be sufficient to successfully run and finish the project. What should you do?

1
done
by
מיין לפי

155. Which is typically not specified in a document referred to as activity attributes?

1
mood
by
מיין לפי

In a country with high level of violence in public, a local police officer requires a private money transfer to ensure the safety of your team. How do you react?

1
done
by
מיין לפי

157. Which is not a type of project review meeting?

1
done
by
מיין לפי

You are performing integrated change control. Which of the following will not be part of what you do?

1
done
by
מיין לפי

You are project manager for a strategic project with a multi-million dollars value assigned by a company that is listed at a US stock exchange. Recent Earned Value Analysis after app. 25% completion told you that your project has a CPI of 0.76. What should you do right now?159

1
done
by
מיין לפי

A management point in a work breakdown structure (WBS) used to consolidate and process work package data and forward the results to the project manager is called

1
done
by
מיין לפי

161. In project management, work authorization is normally not…

1
done
by
מיין לפי

When you perform quality assurance in your project, which technique could you typically use?

1
done
by
מיין לפי