In a project, a cost incentive contract has been awarded to a contractor with the following parameters: Target cost:$1,000,000 Target contractor fee:$100,000 Cost benefit sharing ratio:80%/20% Price ceiling:$1,200,000 What is the point of total assumption (PTA, breakpoint) of the project?46