A project was budgeted at $1,000,000. Meanwhile, the project is executed, and the following current figures have been assessed: PV: $500,000 EV: $450,000 AC: $550,000 Assuming that the cost variance was caused by one-time cost drivers, which are no more effective, what estimate at completion (EaC) can you derive from these figures?