Discuss, Learn and be Happy דיון בשאלות

help brightness_4 brightness_7 format_textdirection_r_to_l format_textdirection_l_to_r

You are assigned as a project manager for an internal project. During cost planning and budgeting you discovered that there are peak times of costs during the project and other times when costs are fairly low. What could this mean for the project?

1
done
by
מיין לפי

You are going to take over a new project as the project manager in an enterprise unknown to you. What should you investigate during the chartering process?

1
done
by
מיין לפי

A project was budgeted at $1,000,000. Meanwhile, the project is executed, and the following current figures have been assessed: PV: $500,000 EV: $450,000 AC: $550,000 Assuming that the cost variance was caused by one-time cost drivers, which are no more effective, what estimate at completion (EaC) can you derive from these figures?

1
done
by
מיין לפי

An organization is considering various contract types in order to motivate sellers and to ensure preferential treatment. What should they consider before deciding to use an award fee contract?

1
done
by
מיין לפי

84. What is least important when it comes to archiving project records?

1
done
by
מיין לפי

85. _______ are not necessarily used to establish the cost baseline of a project.

1
done
by
מיין לפי

You took over a customer project for your company. From the inputs available, including contract, statement of work and project charter, you have developed a project management plan. You already presented that plan in a meeting with key stakeholders including your project sponsor and some representatives from the customer organization. During the meeting you sensed a high level of dissatisfaction by the customer executives, who signaled that the project might not produce the results that their company had expected. In your understanding, all necessary actions have been planned to meet the customer’s requirements. What should you do next?

1
done
by
מיין לפי

A project was assessed and the following earned value data have been found: PV: $750,000 EV: $750,000 AC: $900,000 What is the burn rate of the project?

1
done
by
מיין לפי

88. What is not true for project deliverables?

1
done
by
מיין לפי

Your project, run for a customer, is coming to an end. The customer has been contractually granted a three years warranty period for the product of the project. What should you do first?

1
done
by
מיין לפי